Home>Blogs>Security>What Is a POA&M? CMMC Rules, Template Outline and the 180-Day Limit
What Is a POA&M? CMMC Rules and Template Outline
November 10, 2026

What Is a POA&M? CMMC Rules, Template Outline and the 180-Day Limit

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

A CMMC Level 2 assessment does not have to be a perfect score. Some gaps can be fixed after the assessment, but only on a plan of action and milestones, and only under tight rules. This guide explains what a POA&M is, what can and cannot go on one, and how the 180-day clock works.

What is a POA&M?

A plan of action and milestones (POA&M) is a document that lists each security requirement you have not yet met, the tasks needed to fix it, who is responsible and the dates for each step. In CMMC Level 2, a POA&M can earn Conditional status only if you score at least 80% and close every item within 180 days.

The POA&M is the companion to your system security plan (SSP). The SSP describes what is in place. The POA&M describes what is not, and how and when that will change. The two documents have to agree with each other and with your SPRS score.

When can you use a POA&M in CMMC Level 2?

The rules sit in 32 CFR 170.21. A POA&M is allowed only for requirements scored as not met, and only if all three of these are true:

  • Score: your assessment score divided by the total number of Level 2 requirements is at least 0.8. With 110 requirements, that means at least 88 points.
  • Point value: no requirement on the POA&M carries more than 1 point. The one exception is SC.L2-3.13.11 (encryption of CUI), which may be listed if encryption is used but is not FIPS-validated.
  • Not excluded: none of the requirements in the table below are on it.

A Level 1 self-assessment never allows a POA&M.

Which requirements cannot go on a POA&M?

RequirementTopic
AC.L2-3.1.20External connections (CUI data)
AC.L2-3.1.22Control of public information (CUI data)
CA.L2-3.12.4System security plan
PE.L2-3.10.3Escort visitors (CUI data)
PE.L2-3.10.4Physical access logs (CUI data)
PE.L2-3.10.5Manage physical access (CUI data)

Because most higher-value requirements are also barred, the practical rule is simple: the controls that matter most have to be met on assessment day, and the POA&M is for the small, low-value gaps. Our guide to the CMMC and NIST 800-171 requirements shows how the 110 requirements are grouped.

How the 180-day closeout works

If you pass with a POA&M, you receive Conditional CMMC status. The POA&M items must then be confirmed as closed by a POA&M closeout assessment within 180 days of the Conditional status date. That assessment covers only the requirements that were on the POA&M. If the items are not closed in time, the Conditional status expires.

  • Level 2 self-assessment: your own organization performs the closeout, in the same way as the original self-assessment.
  • Level 2 certification assessment: an authorized or accredited C3PAO performs it.

See the 90-day C3PAO assessment readiness guide for how POA&Ms and conditional status fit into the assessment timeline.

POA&M template outline

There is no single required format, but each item should carry enough detail for an assessor to see that the fix is real, owned and dated:

FieldWhat to write
RequirementThe requirement ID and a short description, copied from your assessment
FindingWhat is not met today and why
TasksThe specific steps that will close the gap
Owner and resourcesThe named person responsible, plus budget, tools or staff needed
Milestones and datesInterim steps with dates, and a final completion date inside the 180-day window
StatusNot started, in progress or complete
Closure evidenceWhat you will show the assessor when the item is done

Common POA&M mistakes

  • Listing excluded requirements. Putting the SSP or a physical-access control on the POA&M does not make the assessment pass.
  • Missing the score threshold. Below 88 points, no POA&M is allowed at all.
  • Vague dates. "Q2" is not a milestone. Each step needs a date inside the 180 days.
  • No owner. An item without a named person does not get done.
  • A POA&M that contradicts the SSP. Claiming a control is implemented in one document and open in the other undermines both.

For the full path from scoping to certification, read the CMMC 2.0 compliance guide.

Frequently asked questions

What does POA&M stand for?

POA&M stands for plan of action and milestones. It is a document that lists unmet security requirements, the tasks to fix them, who is responsible and the target dates.

Is a POA&M allowed at CMMC Level 1?

No. A Level 1 self-assessment never allows a POA&M. All Level 1 requirements must be met.

What score do you need to use a POA&M at Level 2?

You need a score of at least 80% of the Level 2 requirements, which is 88 out of 110 points. Below that, a POA&M cannot be used.

How long do you have to close a POA&M?

You have 180 days from the Conditional CMMC status date. A closeout assessment must confirm the items are closed, or the Conditional status expires.

Which requirements cannot be on a POA&M?

Six requirements are excluded: AC.L2-3.1.20, AC.L2-3.1.22, CA.L2-3.12.4 (the system security plan), PE.L2-3.10.3, PE.L2-3.10.4 and PE.L2-3.10.5. In addition, no requirement worth more than 1 point can be listed, apart from the FIPS-validated encryption requirement SC.L2-3.13.11.

Key takeaways

  • A POA&M lists unmet requirements with tasks, owners and dates, and it is only available at Level 2.
  • You need at least 88 of 110 points, and only low-value requirements qualify.
  • Six requirements, including the SSP, can never go on a POA&M.
  • Every item must be closed and confirmed within 180 days of Conditional status.
What Is a POA&M? CMMC Rules, Template Outline and the 180-Day Limit
Book your free Discovery Call Today!

Embark on the path to efficiency and success by filling out the form to the right.

Our team is eager to understand your unique needs and guide you towards a tailored ClickUp solution that transforms your business workflows.

Start a conversation

Tell us about your project

Share a few details and our team will get back to you with the right next step.

We use your details only to respond to this request. See our Privacy Policy.

Thanks, we have your message.
A member of our team will review it and get back to you soon. If it’s urgent, call us on (703) 844-0918.
Oops, something went wrong. Please try again or email hello@visioneerit.com.